14×7 rotation and other field rotations: how to quote them

Updated on 22/10/2026

In the field, the job doesn't stop when the crew rests. On a 14×7 rotation each position works 14 days and rests 7, so to cover a position every day you need relief staff. That relief gets paid, and if it isn't in your price, it comes out of your margin.

The rotation factor

Factor = (work days + rest days) ÷ work days

RotationFactorWhat it means
6×11.1717% more staff to cover the day off
7×72.00Two people per position
14×71.50One and a half people per position
20×101.50Same as 14×7, with longer shifts
21×71.33One third more staff

Example: a 6-person crew on 14×7

  • Positions covered on site: 6
  • People on payroll: 6 × 1.5 = 9
  • If the real cost per person is S/ 4,500 per month, the crew costs S/ 40,500 per month, not S/ 27,000

On top of that, add everything that is also multiplied per person-day: meals, lodging, transportation to the site, PPE, medical exams, and SCTR.

MIVA Cost automatically applies the rotation factor to labor and per-person-day costs when you choose the project's rotation.

Frequently asked questions

Does the factor also apply to per diem?

Yes, to everything paid per person: per diem, PPE, medical exams, travel to and from the site. Not to equipment or materials.

What if the client pays per day worked?

Then your daily rate must include the cost of relief staff: the monthly cost of the full crew divided by the days you actually bill.

This guide is for reference only and does not replace advice from an accountant or lawyer.